Summary

The school swimming pool in Ichenhausen was outdated and structurally compromised. As part of a larger modernization effort, Build Smart was commissioned to carry out the entire interior demolition and site preparation for a full conversion of the pool facility.

The project posed several challenges:

  • Large volumes of reinforced concrete and ceramic materials

  • Restricted working hours due to school operations

  • Suspected hazardous building materials due to the construction era

  • The need for minimal disruption and complete dust control

Our approach included:

  • Selective gutting of the entire pool area, locker rooms, and technical zones

  • Controlled demolition of the pool basin, platforms, and tile-covered wall sections using vibration-dampened machinery

  • Dust-reduction protocols, including sealed work zones, negative air pressure systems, and active dust suppression

  • Material separation and recycling, with special attention to concrete, tiles, metals, and insulation

  • Asbestos pre-screening, with secure removal of suspected pipe insulation and joint compounds by certified personnel

  • Documentation through before/after photography, work reports, and disposal records

Location

Ichenhausen, Bavaria - Germany

Completion Year

2024